CSM Building 9 – 2009 Renovation Project
Photo of CSM Building 9
Photos Floorplans
Project Description:

CSM Building 9 is home to the CSM Library, KCSM radio and television studios and offices. The project’s objectives are to construct functional improvements to the KCSM FM radio studios, provide upgrades to the library classroom, modernize the building’s restrooms, and fulfill necessary repairs to the building’s system.

Project Benefits:

This project will improve the configuration of FM studio space at KCSM for enhanced functionality and flexibility of programming and student instruction. It will provide aesthetic upgrades and enable more efficient use of the library space. It will resolve heating and ventilating comfort issues in the entire building. The project will modernize and make accessible the public restrooms.

Schedule:
  • Programming/Design: Nov 2008-Jan 2009
  • Construction Documents Phase: Feb-July 2009
  • Bidding: August 2009
  • Construction: Summer 2009 - 2010
  • Completion: TBD
Status: Complete
Project Manager: Linda da Silva
Telephone: 650-358-6726
E-Mail: dasilva@smccd.edu
Architect: Sugimura Finney Architects
General Contractor: To Be Determined
Funding Source(s): Measure A General Obligation Bond Funds

Project Documents

Facilities Planning & Operations
Phone: (650) 574-6512
Fax: (650) 574-6574

San Mateo County Community College District
3401 CSM Drive
San Mateo CA 94402

Construction Planning Department
Phone: (650) 358-6785
Fax: (650) 358-6764

spacer   
   
spacer
spacer

Copyright 2006 © San Mateo County Community College District. All rights reserved.
Questions? Contact the Webmaster
OmniUpdateLast Updated: 5/17/07 9:58 PM