PROJECT NAME: |
|
Skyline Building 1 Theater Seat Replacement Project |
|
|
|
PROJECT DESCRIPTION: |
|
New seats will be installed in the theater to replace the large holes and exposed springs in the original seats that were installed in 1969. The inside of the theater will be cleaned and painted. |
|
|
|
SCHEDULE: |
|
Painting begins on Monday, July 1st. Demolition of the existing chairs will begin on July 9th; installation of the new chairs will begin on July 12th. All work within the theater to conclude by the end of July. |
|
|
|
CAMPUS IMPACT: |
|
All construction activities will be contained within the theater area and disruption should be minimal. |
|
|
|
PROJECT CONTACT: |
|
Please direct any questions or concerns related to this project to: |
|
|
|
NAME: |
|
Karen Pinkham |
EMAIL: |
|
pinkhamk@smccd.edu |
TELEPHONE: |
|
650-358-6714 |