For the beginning of the Fall semester you will be seeing enhanced signage, building identification and decorative banners thru out the campus. This means that for the next 2 weeks there will be various contractors and supplier on campus with special, sometime large equipment.
Beginning Monday, July 29th Coulter Construction and Griffin Painting will be removing old lettering and numbers from numerous buildings. This remove, patch and paint process will continue thru Friday, August 2nd.
Beginning August 7th, VKK Sign Company will on campus to install the new building number and lettering where necessary. They expect to be on campus for 3 days.
Beginning August 5th, Ellis & Ellis sign company will be on campus to install pedestrian and vehicular wayfinding upgrades,banners and parking lot Identifiers. They expect to be on campus that entire week.
All of this activity will involve large lifts and the re-routing of foot traffic.
Thank you for your patience while these upgrades take place |