CAMPUS IMPACT: |
|
Construction will begin at 7:00 am on Wednesday in the KCSM facilities on the lower floor of Building 9. Contractor will access the space through the loading dock on the south side of the building. The work involves demolition and repairs to 1 doorway, 1 set of concrete risers, and the small sound booth on the mezzanine level. There is no real campus impact anticipated with the exception to KCSM staff. Department members will be re-routed away from the area of work to the alternate access around the studios to the north. This path of travel will be permanent. The more southerly access will be for handicapped students, visitors and staff only. Portions of the work will be noisy and dusty. All efforts will be made to mitigate any interruption to normal business activity. A few weeks later, a portable wheelchair lift will be placed at the site of the demolished stairs, again for physically challenged users only. Thank you for your patience during this process, which will make our terrific KCSM program accessible to more of our constituents. |