PROJECT NAME:
CSM Buildings 5/6 Swing Move
PROJECT DESCRIPTION:
Office preparations and moves in Building 1
SCHEDULE:
Saturday and Sunday, May 10 and 11
CAMPUS IMPACT:
Saturday - relocation of furniture and equipment from Rooms 151/153 to 117/121
Sunday - painting and cleaning of rooms 151/153
Thank you for your patience during this busy activity.
PROJECT CONTACT:
Please direct any questions or concerns related to this project to:
NAME:
Michele Rudovsky
EMAIL:
rudovskym@smccd.edu
TELEPHONE:
650 378 7353 650 222 4994
For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at: http://www.smccd.edu/accounts/smccd/departments/facilities/ConImpacts.shtml
Diane Martinez Facilities Operations Manager College of San Mateo (650) 574-6577 (650) 574-6203
Facilities Planning & Operations Phone: (650) 574-6512 Fax: (650) 574-6574