PROJECT NAME: |
|
CSM CIP2 Design-Build Project |
|
|
|
PROJECT DESCRIPTION: |
|
Razing of two colonnades between Buildings 1 and 5
Please note that the colonnades between Buildings 2 and 4, the colonnades east of Buildings 2 and 4, and the colonnades between Buildings 14/16/18 are NOT being razed! Removal of the colonnades will provide for reconstruction of the area in accordance with the 2006 Facilities Master Plan and the project’s approved bridging design, including construction of the new Building 5, accessibility upgrades at the southern end of the campus, and improvements in the area around the reflecting pools. |
|
|
Here’s a bird’s-eye view of the new Building 5, the new Building 10, existing Buildings 1, 2, 4, 8, 9 and 14.
|
SCHEDULE: |
|
Week of July 7, 2008
Demolition will begin at 5:00 a.m. and is anticipated to be completed by 8:00 a.m. Cleanup of the demolished material will occur immediately thereafter. |
|
|
|
CAMPUS IMPACT: |
|
Building 1 is close to the colonnades. Building 1 cannot be occupied during demolition (from 5am to 7am). This should not impact normal college operations. |
|
|
|
PROJECT CONTACT: |
|
Please direct any questions or concerns related to this project to: |
|
|
|
NAME: |
|
Joe Millsaps, Project Manager |
EMAIL: |
|
millsapsj@smccd.edu |
TELEPHONE: |
|
650-378-7347 |
|
|
|
For more information regarding the Capital Improvement Program, please visit the Campus Construction Update page at: http://www.smccd.edu/accounts/smccd/departments/facilities/ConImpacts.shtml |