Arrival Zone #5, located in front of the Book Store Building #2, will have Phased work to allow access to the Building. Please Click Here for more detailed information.
Phase #1 closure areas starts 9/15/08 thru 10/01/08, Book Store ADA and general access will be available from both ends of the Building via the existing ramps; the front stairs will be closed.
Phase #2 closure areas starts 10/06/08 thru 10/24/08, Book Store ADA access will be from the North end of the Building via the ADA ramp. General access will be available from both ends of the Building via the existing ramps; the front stairs will be open for use.
The intent is maintaining continuous access throughout the Work. Thank you for your patience while we make these improvements.
Fence barriers and other safety measures will be in place to separate pedestrians and from construction equipment to minimize disruption to the campus. |