Hello everyone – here’s an update to last week’s Construction Notice -
- This Weekend (April 16 & 17):
- finish painting Bldg 1
- finish painting Portables 3A – 3E
- wash and start painting Bldg 8 (quad facing side)
- Next Monday thru Friday (April 18 – April 22):
- finish painting Bldg 8 (quad facing side)
- wash and start painting Bldg 8 (Vista Point facing side)
- Next weekend (April 23 & 24): finish painting Bldg 8; wash and start painting Bldg 7 (quad facing sides)
Bayview Painting has assured the campus that all entranceways will be accessible during this painting project; entranceways will get painted separately and on weekends only.
Here are the buildings that will get their exterior walls painted (in order) –
- Bldg 5 [Completed]
- Bldg 2 [Completed]
- Bldg 3 [Completed]
- Portables 3A thru 3E
- Bldg 1
- Bldg 8
- Bldg 7 (not the new ½)
- Bldg 9
- Bldg 10
Questions, comments and concerns should be directed to our District Project Manager, Roger Anchartechahar, at ext 6844, Anchartechaharr@smccd.edu.
Thank your patience and cooperation and we move toward beautifying the exteriors of our buildings. Take care –
Richard
Richard Inokuchi
Facilities Operations Manager
Skyline College 3300 College Drive San Bruno 94066
(o) 650-738-4166 (f) 650-738-4113 (c) 650-642-4974
inokuchir@smccd.edu
www.smccd.edu/accounts/smccd/departments/facilities/FPMOMain.shtml
P Please consider the environment before printing this e-mail
Richard
Richard Inokuchi
Facilities Operations Manager
Skyline College 3300 College Drive San Bruno 94066
(o) 650-738-4166 (f) 650-738-4113 (c) 650-642-4974
inokuchir@smccd.edu
www.smccd.edu/accounts/smccd/departments/facilities/FPMOMain.shtml