Hi everyone – here’s a final update -
- This Weekend (May 28, 29, 30)):
- paint the sides of Bldg 8 (that face the Auto areas and Vista Point)
- paint Bldgs 9 and 10 (Auto buildings)
- wash and start painting Bldg 7 (the half of Bldg 7 we used to know as Bldg 7 before the addition)
- Next Tuesday thru Friday (May 31 – June 3):
- paint Bldg 7 (the half of Bldg 7 we used to know as Bldg 7 before the addition)
- painting ’touch ups’ on all buildings that have been painted over the past two months
Questions, comments and concerns should be directed to our District Project Manager, Roger Anchartechahar, at ext 6844, Anchartechaharr@smccd.edu.
On behalf of everyone on the Facilities Maintenance staff – we hope you have an enjoyable and save Summer. Take care –
Richard
Richard Inokuchi
Facilities Operations Manager
Skyline College 3300 College Drive San Bruno 94066
(o) 650-738-4166 (f) 650-738-4113 (c) 650-642-4974
inokuchir@smccd.edu
www.smccd.edu/accounts/smccd/departments/facilities/FPMOMain.shtml
P Please consider the environment before printing this e-mail