Cañada College Central Plant Upgrade
Replace existing 175-Ton Chiller with 500-Ton Chiller at Central Plant at CAN B3
and upsize main chilled water line to 6-inch line at Northeast side B3 to edge of
plaza at Parking Lot 4.
Benefits
Schedule
- Design / Build Pre-Construction Phase: September 2017 – October 2017
- Construction: October 2017 – December 2017
- Completion: Summer 2018
Status
Contact Information
Project Manager
Sajid Sulaiman
650-381-3572
sulaimans@smccd.edu
650-381-3572
sulaimans@smccd.edu
Assistant Project Manager
Apeksha Gajjar
650-381-3574
Gajjara@smccd.edu
650-381-3574
Gajjara@smccd.edu
Architect / Engineer
Western Allied
General Contractor
McCarthy Construction