CSM B36 Mechanical Engineering Project

Replace the existing deficient evaporative cooling/controls with a mechanically cooled system.  Replace two rooftop air handlers and exhaust fans and tie into chilled water system from the Central Plant.  Central Plant water source adjacent to Building 36 as part of the Edison Lot project.

Schedule

DSA Submission: September 28, 2021
Procurement: April-May 2022
Construction: September 2022-August 2024
Occupancy: Fall 2024

Contact Information

Project Manager

  Thomas Lo
  (650) 378-7319
  lot@smccd.edu

Architect

  Salas O'Brien

General Contractor

  Strawn Construction