Skyline College Building 1 Renovation
Improvements include new LED lighting in the Gallery, a new covered area housing the
Ceramic's program's Kilns, AV upgrades in the choral & band rooms, new welding booth
installed in the Sculpture room, a new photography lab, upgraded corridor lighting
and new carpet and paint in many offices.
The network infrastructure will be augmented to provide adequate coverage throughout
the building. Both the roof and mechanical equipment will be ameliorated to support
the building and its improvements in the upcoming years. If the budget allows, improvements
to the theatre, such as new rigging, LED lighting and AV equipment will be included
in the project.
Benefits
Schedule
- Programming/Design: March 2020-July 2020
- Production Phase: July 2020-May 2021
- Bidding: January 2022
- Construction: February 2022-February 2023
- Completion: February 2023
Status
Contact Information
Project Manager
(415) 622-6362
rankh@smccd.edu
Project Assistant
(650) 703-7364
moorhousek@smccd.edu