Cañada College Building 8 MPOE A/C Replacement Project

Building 8 Lobby

Project Description:

The Work generally consists of the removal of the existing A/C system and its replacement with a dual split system in Building 8 for the IDF MPOE data/telephone room.

Project Benefits:

This project will provide adequate cooling to the data/telephone room and provide redundant capacity cooling to protect equipment.

Schedule

  • Issue Advertisement To Bid: July 15, 2011
  • Mandatory Pre-Bid Conference (must attend at least one):
    • July 18, 2011 at 9:00am
    • July 25, 2011 at 9:00am
  • See instructions to Bidders for Pre-Bid conference location and Bid Submittal locations.
  • Addendum #1 issued changing the Bid Date to now be    August 9, 2011 at 2:00pm
  • Addendum #2 issued August 4, 2011 changing the project insurance requirements.
  • Last Day for Pre-Bid RFIs: August 3, 2011
  • Bids Due: August 9, 2011 at 2:00pm
  • Anticipated Notice To Proceed: August 16, 2011
  • Contractual days to achieve Substantial Completion: 45

Status:

Complete

Project Manager:Gogo HeinrichTelephone:650-306-3467E-Mailheinrichg@smccd.eduB Licenced Contractor:TBDFunding Source(s):Funding Sources