Cañada College Building 16 & 18 Renovation
Contact Information
Project Manager
Peter Hempel
Telephone: 650-306-3169
E-Mail: hempelp@smccd.edu
Project Assistant
Sandy Wong
Telephone: 650-306-3463
E-Mail: wongsa@smccd.edu
Architect
Noll and Tam Architects and Planners
General Contractor
Big-D Pacific Builders
Schedule
- Design Phase: September 2003 – June 2007
- Bidding Phase: July - August 2007
- Construction Phase: September 2007 – August 2008
- End of Project: September 2008
Funding Source (s)
Measure C and Measure A Local Bond Funds
Description
The Scope of Work for this project includes the renovation of Science Buildings 16 and 18, and includes a new exterior elevator, restroom renovations, interior accessibility improvements, and new interior finishes. Science labs, prep-rooms, classrooms and faculty offices will also be completely renovated, along with a new data system backbone, Smart classroom technology, and new HVAC systems and controls. New updated equipment and supplies will be provided for the science program.
Benefits
This project will modernize aging science buildings on campus to provide new lab spaces with modern fixtures, equipment and infrastructure, and to renovate the facilities to meet current code and accessibility requirements. When completed, the project will contribute to the successful revitalization of the overall campus experience.
Status
Completed